2024 / PRJ-2024-11
Meridian Geothermal Group
Binary-cycle geothermal plant builder
Geothermal turbine housings, requalified and reshored
A 22-week import lead time and recurring flatness rejections replaced with a single-source domestic route running at 9 weeks.
- 22 → 9 weeks
- Lead time
- 11.4% → 0.6%
- Flatness rejections
- −14%
- Landed cost
- Ongoing since 2024
- Program duration